To use a familiar analogy, if Leo was working on an old timber house,
this would be the progress report:
site establishment -- complete
demolition -- complete
footings -- complete
floor, wall and roof framing -- almost complete
material acquisition -- partially complete
services rough in -- not started
roof sheeting -- not started
external wall sheeting -- not started
floor laying -- not started
external wall sheeting -- not started
internal sheeting -- not started
painting and finishing -- not started
furniture fit out -- not started
So, it might look like the project is better than 60%, but it is really
way less than that...
--
Peter Marquis-Kyle
www.marquis-kyle.com.au
|